| No |
PROFECT |
CLIENT |
CARGO VOLUME |
PROJECT PERIOD |
Sdrvices Provided |
| 1 |
SWWAGE TREATMENT PROJECT |
TAIPEI CITY GOVERNMENT |
3,500 F/T |
1987 |
|
| 2 |
LNG STORAGE TANK PROJECT |
CHINESE PETROLEUM CORP. |
20,000 F/T |
1988 |
|
| 3 |
TOYOTA MOTOR PRJECT |
TOYOTA MOTOR |
15,000 F/T |
1988 |
|
| 4 |
NO.2 RESIDUM DESULPHURIZA TION PLANT / CPC,
TAOYUAN |
CHINESE PETROLEUM CORP. |
3,000 F/T |
1988 |
|
| 5 |
MINTAN PUMPED STORAGE PROJECT |
TAIWAN POWER COMPANY |
30,000 F/T |
1992 |
|
| 6 |
NO.3 RESIDUM DESULPHURIZA TION PLANT / CPC,
TALINPU |
CHINESE PETROLEUM CORP. |
8,000 F/T |
1990 |
|
| 7 |
ELECTROSTATIC PRECIPITA TOR REHABILITATION
PROJECT HSINTA STEAM POWER STATION UNIT NO.1&2 |
TAIWAN POWER COMPANY |
20,000 F/T |
1991 |
|
| 8 |
ELECTROSTATIC PRECIPITA TOR REHABILITATION
PROJECT TALIN STEAM POWER STATION UNIT NO.1&2 |
TAIWAN POWER COMPANY |
15,000 F/T |
1991 |
|
| 9 |
NEI-HU REFUSE INCINERATIN PLANT |
TAIPEI CITY GOVERNMENT |
20,000 F/T |
1990 |
|
| 10 |
SWORO-LAKE MOUNTAIN AMUSEMENT EQUIPMENT |
NISSIN, JAPAN |
8,000 F/T |
1990 |
|
| 11 |
INDUSTRIAL PLASTIC TA-FA PLANT |
CHANG CHUN PETROCHEMICAL CO., LTD. |
7,000 F/T |
1991 |
|
| 12 |
PURIFIED TEREPH THALIC EQUIPMENT |
TUNTEX CO. |
19,000 F/T |
1991 |
|
| 13 |
B-747 FLIGHT SIMULATOR |
CHINA AIRLINES |
1,000 F/T |
1990 |
|
| 14 |
NO.5&6 REFORMING UNIT PROJECT / CPC,
TALIPU |
CHINA PETROLEUM CORP. |
11,000 F/T |
1991 |
|
| 15 |
AIR SEPARATION KUAN-IN PLANT |
SAN FU CHEMICAL CO., LTC. |
3,000 F/T |
1991 |
|
| 16 |
MOCK-UP SYSTEM B767-300ER SIMULATOR and
747-400 SIMULATOR |
EVA AIRWAYS |
1,500 F/T |
1992 |
|
| 17 |
DIESEL HDS UNIT / CPC, TSO-YIN |
CHINESE PETROLEUM CORP. |
250T/PER PC |
1992 |
|
| 18 |
VAL TPE RAIL CAR (DORTS#CC350) |
CEC ALSTOM(MATR) |
102WAGONS / 15,000 F/T |
1992 |
|
| 19 |
RAILWAY WORKSHOP DEPOT(DORTS#CT-309) |
BROWN&ROOT VICKERS TECHNOLOGY LTD |
6,000 F/T |
1992 |
|
| 20 |
MASS RAPID TRAINS (DORTS#C-301) |
UNION RAIL CAR RARTNERSHIP |
132WAGONS /
45,000 F/T |
1993 |
|
| 21 |
HSING-TIEN REEUSE INCINERATION PLANT |
TAIPEI CITY GOVERNMENT |
30,000 F/T |
1994 |
|
| 22 |
SHU-LIN REFUSE INCINERATION PLANT |
TAIPEI CITY GOVERNMENT |
30,000 F/T |
1994 |
|
| 23 |
NA-PU POWER ALANT |
NEM BV |
11,900 F/T |
1994 |
|
| 24 |
HSIN DA POWER STATION / TURBINE&GENERATOR |
TAIWAN POWER COMPANY |
MAX 200 MT |
1995 |
|
| 25 |
CSC NO.2 HOT STRIP MILL / HOUSING |
CHINA STEEL CORP. |
MAX 225 MT |
1995 |
|
| 26 |
FORMOSA CHEMICAL FIBER CORP. REACTOR |
FORMOSA CHEMICAL FIBER CORP. |
MAX 137 MT |
1996 |
|
| 27 |
ICI KUAN-IN NO.2 PROFECT / REACTOR |
ICI |
MAX 220 MT |
1996 |
|
| 28 |
UNCLEAR POWER STATION / ROTOR |
TAIWAN POWER COMPANY |
MAX 225 MT |
1996 |
|
| 29 |
HEAVY HAULAGE IN FORMOSA INDUSTRIAL PARK |
FORMOSA CHEMICAL FIBER CORP. |
MAX 1,105MT |
1996-1998 |
|
| 30 |
CRANE OPERATION IN ERECTION WORK |
SAMSUNG ENG. & CONSTRUCTION CO., LTD |
MAX145 MT |
1997 |
|
| 31 |
SIEMENS MASS RAPID TRAINS |
SIEMENS |
216WAGONS /
65,000 F/T |
1997 |
|
| 32 |
LINKOU POWER STATION / TURBINE & GENERATOR |
SIEMENS |
MAX 225MT
15,000 F/T |
1997 |
|
| 33 |
HAULAGE AND EMBEDDING OF ECT TAINK |
FORMOSA HEAVY INDUSTRIES CORP. |
MAX 600 MT / Total 90ECTs |
1997-1999 |
|
| 34 |
TUNG HSIAO POWER STATION NO.6 / GENERATOR
& TURBINE |
ABB |
MAX185 MT |
1998 |
|
| 35 |
EVER POWER STATION / GENERATOR & TURBINE |
ABB |
MAX235公 MT |
1998 |
|
| 36 |
HEAVY HAULAGE IN FORMOSA INDUSTRIAL PARK
/ REACTOR |
FORMOSA HEAVY INDUSTRIES CORP. |
MAX1,377MT
20,000F/T |
1998-1999 |
|
| 37 |
TRANSPORTATION OF LR1500, 500T CRANE |
SAMSUNG ENG. & CONSTRUCTION CO., LTD |
MAX170 MT |
1999 |
|
| 38 |
TRANSPORTATION OF CC4800, 800T
CRANE |
VAN SEUMEREN |
|
2000 |
|
| 39 |
CHI MEI CORPORATION, EXPANSION OF ABS PLANT |
CHI MEI CORPORATION |
MAX160 MT
3,000F/T |
2000 |
|
| 40 |
REPLACEMENT OF STATOR OF TUN-HSIAO POWRE
PLANT NO.4 |
ALSTOM(ABB) |
MAX220 MT |
2000-2001 |
|
| 41 |
HSIN DAR POWER STATION / DESULPHURIZATION
EQUIPMENT |
I.H.I |
10,000 F/T |
2000-2001 |
|
| 42 |
HOPING POWER PLANT |
ALSTOM |
MAX320 MT |
2000- |
|